Step 1: Buy the hotel
Cost: $100,000-$175,000 per room, but varies across the state. Time: 2-3 months negotiations, not including escrow.
Step 2: Get approval from the city
Cost: Hard to quantify, but the quicker the cheaper. Time: 1-2 years, but much quicker if the governor gets his way.
Step 3: Construction (finally!)
Cost: Less than $10 million, but will vary according to type of homeless housing. Timing: 6-12 months, but will vary according to type of homeless housing.
Step 4: Running the building
Cost: $10,000 per unit per year (but varies) .Timing: Ongoing.